[ARCHIVED] CONSTRUCTION PROJECT UPDATE: Wayne St. & High St.

Wayne High Project

For the first several weeks of the project, the contractor will focus their efforts on Wayne Street between Cole Street and Jameson Avenue and then gradually move east towards Central Ave.  The limits are Wayne Street from Cole St. to Central Ave. and High Street from Metcalf St. to Central Ave.  

The components of the project include selective walk replacement, ADA ramps, curbs, drainage, pedestrian safety  enhancements, traffic signal upgrades, waterline adjustments, and resurfacing.   

The cost of the project is $3,337,964 and is being funded through ODOT STP and SAFETY funds, City of Lima Gas Tax funds, and City of Lima Storm Water and Water Utility Funds.

$ 702,000 –    ODOT STP funds

$1,905,000 –   ODOT Safety funds

$136,516.91 – Gas Tax 309

$140,419.55 – Utilities Account Water

$454,008.20 – Storm Water Large CIP 

TOTAL: $3,337,964.66

 

Sincerely,

Kirk Niemeyer

City Engineer

Facebook Twitter Email

Other News in In the News

AdobeStock_62385421

Security Camera Database

Posted on: September 20, 2023
square

City Focus

Posted on: September 18, 2023
3rd Quarter Newsletter

Our Community Newsletter

Posted on: July 3, 2023