PAVEMENT MILLING SCHEDULE:
April 17, 2019 -
Boyer Avenue (Edwards Street to railroad)
S. Sugar Street (railroad to E. Kibby Street)
April 18, 2019 -
S. Sugar Street (E. Fourth Street to railroad)
Florence Avenue (Second Street to Dead End)
April 19, 2019 -
Norval Avenue (Tenth Street to W. Fourth Street)
April 22, 2019 -
Holly Street (W. Kibby Street to railroad)
April 23, 2019 -
S. Elizabeth Street (W. Kibby Street to Ottawa River Bridge)
PAVING SCHEDULE:
April 22, 2019
Boyer Avenue (Edwards Street to railroad)
S. Sugar Street (railroad to E. Kibby Street)
April 23, 2019
S. Sugar Street (E. Fourth Street to railroad)
Florence Avenue (Second Street to Dead End)
April 24, 2019
Norval Avenue (Tenth Street to W Fourth Street)
Holly Street (W. Kibby Street to railroad)
S. Elizabeth Street (W. Kibby Street to Ottawa River Bridge)